Planning
Solution
Construction
FEATURED PROJECT
At the end of December 2021, 54% of the construction period had elapsed. Although three winter storms created some variance to start the new year, the project continues to move along at a great pace. Exterior work included the installation of precast panels in the CTE wing and steelwork in the auditorium for the balcony, catwalks, and fly loft structures. Temporary enclosures were created in several areas to allow for temporary heating.
INDUSTRIAL
ACI Mechanical received the contract for the $9-million-dollar Mechanical portion of the project and completed detailed layout drawings for the installation. ACI installed 90,000 pounds of galvanized and stainless steel ductwork, installed 29 air handling units, and 10,000 feet of Hydronic Piping.
Construct a state of the art facility that includes a total temperature controlled facility with redundant air handling systems with HEPA filter housing and a building waste system that can be contained in storage tanks prior to being transferred to process waste building, ensuring that the environment is not exposed to potentially dangerous and contagious pathogens.
INFRASTRUCTURE
ACI Mechanical assembled a project team of talented engineers, including civil, structural, and landscaping as well as specialty subcontractors to in order to submit a $17.3 million dollar GMP and construction methodology to HAS to install a replacement overhead piping system with routing plan and support structures.
MORE
PROJECTS
Iowa State University Marston Hall – Ames, Iowa
ACI Mechanical used the delay to completely BIM model the mechanical systems. Â A constant flow of field measurements were transferred back to our modeling team. Â The model produced a coordinated layout which allowed our manufacturing facility to prefabricate four floors of ductwork and HVAC piping mains and branch lines. Â Extensive prefabrication reduced our rough-in durations by two weeks per floor, allowing the finishing trades an equal headstart. Â